Education

Modular school in Tsiyab-Tsilitli, Dagestan

A 1,475 m² school built in 60 days. A site camera recorded the entire construction: the timelapse shows the site going from bare ground to a finished building with landscaped grounds.

Facility type
Secondary school
Region
Republic of Dagestan, Gumbetovsky District
Total area
1,475 m²
Year completed
2026

About the project

The Novotsilitlinskaya secondary school of the Gumbetovsky District was built using modular technology for the Ministry of Education and Science of the Republic of Dagestan. The village of Tsiyab-Tsilitli sits on the plain, far from major construction bases, so factory readiness was decisive: building components arrived from the plant ready for assembly.

The site camera recorded the works from 31 July to 4 October 2026. In August a long single-storey building was assembled on the prepared base: classrooms along the main corridor, an administrative block and a sports hall at the end of the building, taller than the main block. By the end of the month the building was roofed and its facade finished. September went into landscaping: paving the yard, fencing, outdoor lighting and planting. The full construction cycle took 60 days. Commissioning date: 1 September 2026, in time for the start of the school year.

The engineering systems are installed inside: a switchboard room with metering and incoming devices, distribution along the corridors, heating and ventilation. Modular technology does not mean simplified services: the scope matches that of a conventional building.

The facade is assembled from factory-painted panels. The colour inserts are specified in the design and need no on-site painting, which shortens the schedule and removes any dependence on the weather during finishing.

Timelapse from site

Construction timelapse: Modular school in Tsiyab-Tsilitli, Dagestan, 31 July to 4 October 2026

Facility specification

Client
Ministry of Education and Science of the Republic of Dagestan
Facility
Novotsilitlinskaya Secondary School, Gumbetovsky District
Total area
1,475 m²
Construction time
60 days
Timelapse period
31 July to 4 October 2026
Commissioning
1 September 2026
Storeys
Single storey
Walk around the finished school
The Tsiyab-Tsilitli school: sports grounds, facades and yard, 6 October 2026
Location
Secondary school

Tsiyab-Tsilitli village, Gumbetovsky District, Republic of Dagestan

43.4832° N, 46.6792° E

Secondary school: Modular school in Tsiyab-Tsilitli, DagestanOpen in Yandex Maps
Discuss a project

Tell us about the task, we will prepare a costing

We will clarify the building purpose, area, region and schedule, then come back with a preliminary costing and layout.